Releases roll out in order: a disposable VM (the converge VM test), then role canaries (one Pi for the resolver role, one x86 host for shared changes), then the second Pi resolver after the first passes sustained checks including a reboot, then the valley host and the remaining hosts after the soak period. Neither resolver reboots or converges while its peer is unhealthy.
Kernel and bootloader changes on the Pis stay supervised until boot-count fallback is demonstrated, with rescue SD images on hand (R3).
Done when a release reaches the canary Pi first and the rest of the fleet only after the soak.
Source: `plan.md` M2 (D4) and "Rollout order"; the deployment project's `ROADMAP.md` D4.
Comments
contributor2026-11-08 22:30 UTC
Duplicate of the deployment project's rollout outcome, named in target: one host takes each release first, and the others follow once it stays healthy.