Velocity has dropped to a crawl because the checks run at approval take so long (operator, 2026-10-22). `attest run` evaluates and builds each check in turn (attest/run.go around 110, attest/check.go around 150): one flake evaluation and one `nix build` per check, so the wait is the sum of 17 to 35 checks, including VM tests, while the workstation's cores sit idle.
Evaluate the required checks once, then build every derivation in one `nix build --keep-going`, so Nix schedules them concurrently. Each check keeps its own outcome and statement: derivation, inputs, output, pass or fail. The evidence format is unchanged. Done when a change requiring many checks finishes in roughly the time of its longest check plus evaluation, the per-check records match what the sequential run produced, and one failing check neither stops the others nor loses its log.
Comments
contributor2026-10-23 02:16 UTC
Change valley:the-valley/nowtwuzrqpqtqnuntzurqsxtrpowrlru landed: v4 as 5b2f94ebeb023d117d44620cefda0dc67ce9e5ae.
Every change the knot links has landed and it has no active children, so klaus set it done.